Power From Manapouri - Construction Brochure

  • Author: Unknown
  • Date: 1967
  • Source: Reproduced from a PDF photocopy of the brochure (original in pdf here)

Construction Brochure: Front Cover
Front Cover
Construction Brochure: Inside front cover
Inside front cover

Vast and Majestic

The Manapouri-Doubtful Sound hydro-electric project is in Fiordland National Part, which is in the Southland district of the South Island of New Zealand. The project draws on Lake Manapouri for water, which will drop vertically 700ft to an underground powerhouse and then flow through 6 miles of tunnel to discharge in the sea at Deep Cove in Doubtful Sound.

  • Fiordland National Park is a vast region, majestic in scenery. Of 3 million acres, it is one of the world’s largest parks and occupies the entire south-western sector of the South Island.
  • Gaunt Peaks and sheer rock walls typify its mountain ranges and reflect the extensive glaciation of relatively recent geological times. Glaciers retreating left chasms which became fiords and dammed valleys which became beautiful lakes.
  • The largest lake is Te Anau, which covers 138 sq. miles and is 663 ft above sea level in a great glacial basin. The mall township of Te Anau is at its southern end.
  • Lake Te Anau is linked to the nearby Manapouri (lake of the sorrowing heart) by the south-flowing Waiau River. With forested islets and surrounding high mountains, Manapouri is considered the most beautiful lake in New Zealand. It is 80ft lower than Te Anau, covers 55 sq. miles, and is the deepest lake in the country with a maximum sounding of 1,455ft (872ft below sea level).
  • To the west, rugged mountains, on which forest runs up to snow, separate these lakes from the Tasman Sea, where the coastline of deeply indented fiords is of great beauty. This region is among the world’s greatest tourist attractions.
  • Hydro-electric development was first considered in 1904, but the scheme to use the waters of Te Anau and Manapouri in a 600ft fall through the mountains into the sea at Doubtful Sound was put aside because of its magnitude and the inaccessibility of the area.
  • In 1959 the scheme was revived because of a proposal to build an aluminium smelting plant at the deep-sea port of Bluff, near Invercargill. Investigations were begun at West Arm on Lake Manapouri by Comalco Industries Proprietary Ltd, of Australia, but in 1963 the New Zealand Government assumed responsibility for the development. Comalco, however, retained an option on part of the electrical output.

How This Land Was Formed

The high mountains around Te Anau and Manapouri are mainly of schist and gneiss. Both are formed by the alterations, or metamorphism, of ancient sedimentary and volcanic rocks that were themselves formed at great depth in the Ordovician period 450 million years ago. Later, by slow uplift and erosion the present mountain ranges emerged.

During their burial in the Cretaceous period, 100 million years ago, the earth temperatures and pressures were very high, and new minerals were created, such as the mica that gives schists their sheen and the quartz and felspar that make the gneisses like granite. Sulphides, including those of copper, are common in these rocks, but they occur only as minute crystals, and concentrations are not economic.

Construction Brochure: Map of NZ
Map of NZ

Both types of rock are clearly exposed around the fiords, and in the walls of the access and tailrace tunnels of the Manapouri Power Development, where evidence of their former deep burial is shown by intensive shearing, and by veins of white quartz and pegmatite which criss-cross through the gneiss in fantastic patterns. In the later Oligocene period, 35 million years ago, limestones were deposited on schist and gneiss. In them are extensive caves across the lake from Te Anau that are visited by tourists.

The landforms of Fiordland were carved out of the extremely hard rocks in Pleistocene (Ice Age) period that lasted from three million to 10,000 years ago. Ice itself was the main agent. Glaciers carved deep gorges during their slow movement to the sea. In the west, they formed fiords, like Doubtful Sound, whose steep sides continue deeply below sea level. Smaller subsidiary glaciers left mush shallower valleys.

In the east the glaciers melted away in the river valleys and vast quantities of rock and clay in the ice were deposited as moraine around the ice snout. The irregular hills at the southern ends of Te Anau and Manapouri lakes were formed from the old moraines of glaciers.

Upstream, the glaciers carved the deep valleys of the lakes: and downstream the rivers carried away boulders and clay to leave extensive river flats.

Location and Access

Construction Brochure: Access Map
Access Map

The hydro-electric development is between the head of the West Arm of Lake Manapouri and Deep Cove at the head of Doubtful Sound, including the Wilmot Pass.

From Invercargill, Manapouri can be reached by road, by rail and road, or by air.

By road the distance is 99 miles on a sealed highway. Buses leave Invercargill daily, connecting with launches on Lake Manapouri. Buses also leave from Lumsden for Manapouri and Te Anau.

The railhead for Manapouri is Mossburn, 49 miles to the east.

Air travel is by private charter amphibians from Invercargill and Te Anau.

West Arm is reached by launch from Pearl Harbour, Manapouri. The 80-seat launch Fiordlander leaves regularly for the West Arm site, and the 20 mile journey takes an hour.

Amphibians fly from Te Anau or Manapouri by special arrangement.

Doubtful Sound, formerly accessible only by sea or amphibian, is now served by a bus service, from West Arm, Lake Manapouri, by way of the Wilmot Pass road.

In the interests of public safety, visitors are not permitted to tour the engineering site unless in arranged parties approved by the Bechtel Pacific Corporation or the New Zealand Government. During the earlier part of the work the Wilmot Pass road carried only heavy construction traffic.

Construction Brochure: Mountain view
The mountains between Doubtful Sound (foreground) and West Arm, Lake Manapouri (background) rise to 4,000ft above the tailrace tunnel route.
Construction Brochure: West Arm
West Arm, Lake Manapouri, at earliest stage of project.
Construction Brochure: Manapouri township
Manapouri township looking towards Wets Arm. The Lower Waiau River in foreground.
Construction Brochure: Wanganolla
Wanganolla moves to her mooring in Deep Cove in August 1963. In centre, the Lyvia Valley rises to the 2,200ft Wilmot Pass, which the road to Manapouri now crosses.

 

Names and Places

Lyvia River

Lyvia River was named by Captain J.L. Stokes of HMS Acheron when he explored Doubtful Sound in 1851. Previously it had been called by the Maori Kahui-kakapo, “meeting place of the kakapo”.

Hall Arm

Sailing down Malaspina Reach in Doubtful Sound and passing Rolla Island, the traveller finds Hall Arm opening out to his right and running southwards. He is almost immediately among jagged, towering heights. To the west of the entrance, Commander Peak with its outjutting top looms 4,000ft above Davidson Head. Travelling the narrows he finds himself in a great rocky corridor with the view ahead of stark peaks dominated by Mount Danae (4,800ft). Towards the end of the arm the view softens. The lower slopes of the great mountains are covered with a profusion of native bush broken here and there by waterfalls. Hall Arm was named by Captain J.L. Stokes of HMS Acheron when he explored Doubtful Sound in 1851. It is not known who Hall was.

Construction Brochure: South Arm, Lake Manapouri
Early view of South Arm, Lake Manapouri, showing Grebe Valley which the transmission line will follow. South Arm camp site is now built on right bank of Grebe River.

Brasell Point

Brasell Point is at the southern end of Deep Cove and was named by the New Zealand Geographic Board for Mr George Brasell, owner and master of the ship Miss Akaroa. Mr Brasell, born at Lyttleton, was in his youth a yachting champion and become a notable trawler skipper whose superior seamanship contributed to several successful search and rescue operations. In recent years he used Miss Akaroa for survey work on the Fiordland coast.

Te Anau

This name is said to have been given to the lake by the high chief Rakiahautu about A.D. 850. Landing in Nelson, he worked his way down the middle of the South Island, naming the long chain of lakes there. Te Anau is probably more correct as Te Anau-au, which means “cave of swirling waters”, for the caves at Tunnel Burn.

Doubtful Sound

On his first voyage to New Zealand in 1770 Captain James Cook gave the name Doubtful Harbour to what is now known as Doubtful Sound, apparently because he doubted is a ship, once in the inlet, could return against the prevailing westerly winds.

Wilmot Pass

One the walking route between the head of Lake Manapouri and Deep Cove in Doubtful Sound, this pass was discovered in 1888 by R. Murrell. He was searching for Professor Mainwaring-Brown, who had been lost while exploring the valley of Disaster Burn. The pass was named for the surveyor E.H. Wilmot, who some years afterwards confirmed Murrell’s discovery.

Construction Brochure: Surveyor
Surveyor sighting in tunnel to ensure correct alignment.

Manapouri

Manapouri was one of the lakes named by the high chief Rakaihautu when he visited New Zealand in his canoe Uruao about A.D. 850. He called it Roto-ua (rainy lake), but it later came to be known as Moturau, either because of the literal meaning of the word (hundred islands) or because of the legend that the lake was formed by the tears of two sisters, Moturau and Koronae.

Moturau was also the name given to the lake in 1852 by the first Europeans to discover it, C.J. Nairn and W.H. Stephen. It is thought that in 1862 surveyor James McKerrow misinterpreted this name for Manapouri, a variation of Manawapouri, which is usually translated as “lake of the sorrowing heart”.

Construction Brochure: Manapouri map
Manapouri map

The Development

Of a planned capacity of 700,000 kilowatts of electricity, the Manapouri hydro-electric scheme involves diverting water from Lake Manapouri through an underground powerhouse at the head of the West Arm of the lake. The water then leaves by tunnel to discharge into the sea at Deep Cove at the head of Doubtful sound.

The scheme can be divided into seven sections:

  • A tailrace tunnel under the mountains from Deep Cove to the underground power house at West Arm on Lake Manapouri.
  • A tunnel to give access to the site of an underground powerhouse at West Arm.
  • The subterranean chamber for the underground powerhouse, and on the surface, the associated control buildings and switchyard.
  • A highway over Wilmot Pass to link the two phases of the development.
  • Access roading and bridging for the erection and maintenance of transmission lines.
  • Transmission lines.
  • Control works on the Waiau River.

To complete the scheme in five years requires careful planning. In principle the scheme is simple, for there is no major dam and much of the work is tunnelling. However, the project has unique problems.

Remoteness, difficult access and communications, heavy rainfall (250 in. annually), snow, and sandflies affect not only progress of the work but also the well-being of the men employed.

Accommodation for the hundreds of workers on the tailrace tunnel at Deep Cove was a major problem, for Deep Cove is a wet and lonely place. Isolated by high mountains, rising almost vertically from the water, Deep Cove, before the project began, was accessible only by sea or over Wilmot Pass.

For accommodation the contractors bought the trans-Tasman liner Wanganella, which in August 1963 was converted into a floating hostel at Deep Cove. The Wanganella also served as a floating dock, her derricks being used to unload stores and equipment.

As Deep Cove was the best access for heavy plant and equipment for both Deep Cove and West Arm, a new cantilever wharf, suitable for ships up to 13,000 tons, has been built close to where the Wanganella is berthed. Building the wharf was difficult, as there were no shelves on which to place foundations, the steep mountainside continuing straight down beneath the water for several hundred feet.

Port-of-entry customs regulations apply, as do precautions against introducing pests, or human, animal, and vegetable diseases.

A resident policeman has these responsibilities in addition to his normal duties.

Construction Brochure: Accommodation ship Wanganella
Accommodation ship Wanganella with Southern Scenic float plane in Deep Cove.
Construction Brochure: Sleeping accommodation Wanganella
Sleeping accommodation for workmen on hostel ship Wanganella.
Construction Brochure: The library on the Wanganella
The library on the Wanganella.
Construction Brochure: Dining accommodation Wanganella
Dining accommodation on hostel ship Wanganella at Deep Cove.
Construction Brochure: Ambulance on the Wanganella
Ambulance on the Wanganella at Deep Cove is ready 24 hours a day. Mount Barber is in background.
Construction Brochure: Schie Lloyd
Schie Lloyd, first overseas vessel to berth at the new cantilever wharf at Deep Cove, unloading the first generator for the powerhouse at West Arm.
Construction Brochure: Wharf at Deep Cove under construction
Permanent wharf at Deep Cove under construction. The 150x53ft wharf will be used by ships up to 13,000 tons.
Construction Brochure: Police officer on Wanganella signs customs papers
New Zealand Police officer on Wanganella signs customs papers.
Construction Brochure: The electricity generating powerhouse at Deep Cove
The electricity generating powerhouse at Deep Cove, large enough to supply a moderate-sized city.
Construction Brochure: Manufacture of pipes
Manufacture of pipes.
Construction Brochure: Servicing installation, tailrace tunnel at Deep Cove
Servicing installation, tailrace tunnel at Deep Cove. Tailrace portal is behind the buildings.
Construction Brochure: Portal of tailrace tunnel at Deep Cove
Portal of tailrace tunnel at Deep Cove. Pumping station is on right.
Construction Brochure: Switchyard inside tailrace tunnel
Switchyard inside tailrace tunnel.

The Tailrace Tunnel

Construction Brochure: Drilling jumbo, No. 3, tailrace tunnel, Deep Cove.
Drilling jumbo, No. 3, tailrace tunnel, Deep Cove.
Construction Brochure: Explosive truck at face of working.
Explosive truck at face of working.

The tailrace tunnel, driven under the mountains from Deep Cove to the underground powerhouse at West arm, and 32,250ft long (6 miles), has a modified horseshoe section 30ft high, reinforced with rockbolts and wire mesh and lined throughout with concrete.

The tunnel was begun on 4 February 1964, when the Prime Minister (Mr Holyoake) fired the first shot. Drilling and clearing the debris were done by simple mechanical methods at first and trucks were used to remove spoil, but later a railway system was laid and more advanced tunnelling techniques were used, enabling the work to be done quicker.

Construction Brochure: Drilling and firing pattern, tailrace tunnel.
Drilling and firing pattern, tailrace tunnel.
Construction Brochure: Servicing area
General view of servicing area at Deep Cove end of tailrace tunnel. Portal is at top left of photo
Construction Brochure: Drilling from jumbo in tunnel
Drilling from jumbo in tunnel.
Construction Brochure: Muckers at work removing spoil from face
"Muckers" at work removing spoil from face.

The rail trucks, each with a capacity of 14cu. yd., are drawn by electric locomotives, and dump must of the rock spoil at the head of Deep Code to form a spillway embankment, the rest being used as aggregate for concrete to line the tunnel. About 32cu. yd. of spoil is removed for each foot of tunnel driven,

A 45-ton steel jumbo, or drilling rig, was built inside the tunnel. Mounted on rails laid along the extreme sides of the tunnel, the jumbo is 23 ft high and has four platforms at various levels, carrying up to 18 high-speed drills, driven by compressed air. The drills bore 4 to 30ft into the rock face, depending on the type of rock. The jumbo is moved to the face for drilling but is moved back 450ft during blasting.

Drilling is to a specific patter, which is shown in the accompanying illustration. All except the centre three holes are packed with explosive charges, wired and fired electrically, in the sequence shown by the numbers, at intervals of half a second. The centre holes are made bigger than the others, so that when the initial charge (No. 1) is fired the weakened centre offers little resistance and the debris falls into it. Later firings are designed similarly, the aim being to disturb the roof as little as possible.

Explosives are brought to the face in a special rail truck under strict safety precautions. While the charges are being placed, wired, and fired, the men go behind the firing box, at least 1,000 ft from the face.

All electricity is disconnected, the men placing the charges working in darkness.

After a blast two special rail-mounted mucking machines, or mechanical shovels with conveyors, automatically load the spoil into tipping rail trucks designed for the job. The muckers can deliver several tons in a few minutes.

A switchyard at the face enables the trucks to be shunted. After a complete blasting and excavating operation the switchyard, which is mounted on a sliding steel floor, is moved forward by hydraulic jacks to the new face. A single railway line is then added to the rear of the floor and the tunnelling sequence is ready to start again. This is the first time such a method has been used in New Zealand.

Wet, humid conditions prevail in the tunnel as it penetrates deeper into the mountains and water pours continually from the face and at points along the unlined portion. Some 5,000 gallons of water a minute are pumped from the tunnel.

Concreting

Lining the tunnel with concrete is necessary to prevent erosion of the walls and to ease the flow of water. The lining will average 15in. in thickness, and to prevent high external hydraulic pressure on its surface a pattern of drainage holes will be drilled through the lining into the rock. In local areas, where the rock is less solid, the concrete lining is being reinforced.

The huge quantities of cement for the job are shipped in bulk to Deep Cove and are transferred by suction to three big silos ashore.

Construction Brochure: Cement vehicle
Cement vehicle, batcher, and rail mixer trucks, Deep Cove.
Construction Brochure: Finished portion of tailrace tunnel, fully lined
Finished portion of tailrace tunnel, fully lined.
Construction Brochure: Cement ship, Ligar Bay
Cement ship, Ligar Bay, unloading bulk cement at Deep Cove. Wanganella in background.
Construction Brochure: Concrete aggregate plant
Concrete aggregate plant at servicing area, Deep Cove.

A special vehicle, carrying up to 17 tons in its two hoppers, transfers the cement from the silos to a batching plant about a mile away, where it is mixed with aggregate and batched into specially designed rail mixing trucks. With additives and water in proper proportions, the mixer on the truck is rotated electrically for six minutes before starting its journey into the tunnel.

Underground, the concrete is fed on to a conveyor, build on to a tunnel-shaped, rail-mounted formwork 96 ft long. Men working inside the form – between it and the rock walls, and often with only 12in. of head room – see that the concrete is properly placed and compacted.

All mixes of concrete are thoroughly tested in a laboratory by technicians to ensure they will withstand the stresses that will be applied to them.

Construction Brochure: Concrete samples being tested in laboratory.
Concrete samples being tested in laboratory.

Deep Cove Workshops

The equipment and machinery used at Deep Cove require constant servicing and, to do this, extensive workshops have been built. Fully equipped, they are also geared to manufacture the air ducts and pipes used in both the tailrace tunnel and the access tunnel at West Arm.

A powerhouse, with enough capacity to light a moderate-sized city, has been built in a clearing on the mountainside, and an air-pumping station to supply the air-powered drills and tools has also been erected.

Construction Brochure: Formwork in the 6 mile, 30-ft-high, tailrace tunnel.
Formwork in the 6 mile, 30-ft-high, tailrace tunnel.

West Arm

While work began at Deep Cove, land was cleared at the head of West Arm, Lake Manapouri, and buildings put up for the men and machinery to construct the access tunnel to reach the site of the underground powerhouse, intakes, penstocks, control buildings, and switchyard.

Construction Brochure: West Arm Camp, Lake Manapouri.
West Arm Camp, Lake Manapouri.

Stores and equipment were ferried across the lake by barge, and an electric generating plant and workshops were erected near the lake shore. Later, a large gymnasium with a small store was built for all the male population. A post office was opened in another corner of the gymnasium building to provide full postal and banking facilities. A well appointed wet canteen was built in front of the building.

At first the only way to reach the site, except by air, was by launch Fiordlander, which ran a twice-daily service from Manapouri. Now the contractors run their own two launches, Endeavour and Resolution, to transport workers and small stores.

Across the lake, beside the Manapouri village, a construction village is being built to house many married workers, and these men will be taken daily to and from the project by the launches.

Construction Brochure: Supply Bay to West Arm, Lake Manapouri
Unloading barge from Supply Bay to West Arm, Lake Manapouri.
Construction Brochure: Mess hall, West Arm camp, Lake Manapouri
Mess hall, West Arm camp, Lake Manapouri.
Construction Brochure: Manapouri construction workers' village
Manapouri construction workers' village.
Construction Brochure: Resolution and Endeavour at Supply Bay
Launches Resolution and Endeavour at Supply Bay.
Construction Brochure: West Arm camp
West Arm camp from lake with launch Fiordlander in foreground.

Access Tunnel

Construction Brochure: service shaft above powerhouse
Using permanent service shaft above powerhouse, muck skip raises spoil in two minutes against 40 minutes through the 1 1/4 mile access tunnel.

Work on the access tunnel began in January 1964. It is 6,700ft long, with a modified horseshoe section 22ft wide, driven on a gradient of 1 in 10, and spiralled to enable heavy plant to be taken by road transporters to the powerhouse. The roof of the tunnel is not lined with concrete, but is reinforced throughout with rock bolts and wire mesh.

Tunnelling techniques similar to those used in the tailrace tunnel were employed, but no railway tracks were laid. Crawler machines were used and spoil was taken to the surface by heavy trucks.

Some spoil from the tunnel was used to help build Wilmot Pass road and West Arm camp, the remainder being dumped and spread on swampy land where Spey River joins Lake Manapouri.

To remove foul air from the face and tunnel, big battery-operated extractor fans were fitted, and compressors supplied air to work the drills and some of the pumps.

Construction Brochure: machine hall of the powerhouse.
Excavation in progress for the machine hall of the powerhouse.

Powerhouse

Rock where the powerhouse gallery is being excavated is expected to be good, and so the gallery is designed to be unlined, but reinforced by grouted rockbolts. Only the minimum excavation is being made.

The powerhouse machine hall, 700ft below the surface, is to be 364ft long and 59ft wide and will house seven turbo-generators, each of 100,000 kilowatts capacity. The underground building will have several floors and will be 128ft high.

The powerhouse layout will be of seven units, each comprising a generator, a transformer, a circuit-breaker, and a switch bay.

Turbines

Only four turbines are to be installed initially. They are of the Francis type and are rated at 142,000 horsepower at 250 revolutions per minute under a net head of 490ft of water. The turbines can be serviced from above.

Generators

Each generator will have a continuous rating of 105,000kVA at 0.95 power factor. The generator voltage will be 13.8kV and the frequency of 50 cycles will be the same as that of the national grid.

Transformers

Eight vaults are to be excavated near the downstream wall of the machine hall to house seven service transformers and one spare.

Each generator will be connected to its corresponding transformer by a segregated phase metal-enclosed bus.

Two 145-ton overhead travelling cranes are to be installed in the machine hall, in which an air-conditioning system will control temperature and humidity. Sufficient air will be exhausted up the cable shafts to control any heat ride in the shafts; and a system to exhaust air from the access tunnel is planned.

Attendants will get to the powerhouse mainly by a service lift, for which the old exploratory shaft was enlarged. It will connect the machine hall with the control building and will also serve as access to cable inspection platforms within the shaft. In the shaft also are the air intake and exhaust ducts and an emergency escape ladder.

Switchyard or Outdoor Station

A switchyard or outdoor station is to be on the surface immediately above the machine hall. Occupying an area of 400ft by 140ft, it will serve three outgoing 200-kV transmission lines and could serve a forth if needed. Transmission from the transformer vaults to the switchyard will be through shafts.

Construction Brochure: Workings in access tunnel, West Arm
Workings in access tunnel, West Arm.
Construction Brochure: Schematic layout of complete power plant, West Arm, Lake Manapouri
Schematic layout of complete power plant, West Arm, Lake Manapouri.
Construction Brochure: Perspective of Manapouri power scheme
Perspective of Manapouri power scheme. (Compare with aerial view of district earlier.)

Intakes and Penstocks

All seven intakes and penstocks are to be built initially, and each turbine will have its own water supply.

Control of the intakes will be by fixed wheel gates designed to work under unbalanced hydraulic conditions. An air duct will be built into each gate shaft, and individual maintenance chambers, with hoisting gear mounted above them clear of lake level, will be provided.

A single upstream sealing bulkhead gate will be installed for use in any of the seven intake shafts. A gantry crane, moving on rails mounted on the maintenance chambers, will allow installation of the bulkhead gate and general maintenance.

The 12-ft-diameter penstock shafts are to be rockbolted and then concrete lined for their first 110 ft, after which a transition to steel lining will take place. The space between the lining and the rock will be filled with concrete.

Construction Brochure: Work at powerhouse face, jumbo in position.
Work at powerhouse face, jumbo in position.

Draft Tubes, Manifold, and Surge Chamber

Each turbine will exhaust into a draft tube. Of the elbow type, the tubes will be lined with concrete, and the cone and elbow with steel. Hinged gates with hydraulic operators will allow each tube to be closed for dewatering.

Water discharged from each draft tube will enter a manifold – a vertical-sided, horseshoe-shaped gallery – which is to be reinforced with rockbolts, wire mesh, and mortar. The tube will vary uniformly in width from 21ft to 36ft and in height from 17½ ft to 50 ft, the greatest dimension being at a point where the surge-chamber shaft is located. At the end of the manifold will be 42ft high.

The surge chamber, required at the closed end of any long conduit, will dampen pressure fluctuations which occur regularly during normal hydro station operations and can be accentuated by rapid loss of sudden increase in load.

Construction Brochure: Switchyard under construction, West Arm
Switchyard under construction, West Arm

Control Building

The control building will be above ground at the top of the service lift shaft. Of reinforced concrete, it will be the nerve centre for the development, containing offices, control room, cable spreading room, and machinery for ventilation and lift control. Access will be by road past the intake structures. A lift from this building will give access to the machine hall.

Wilmot Pass Road

The two major phases of the development are connected across Wilmot Pass by a highway, constructed in rigorous climatic conditions. Both ends were started about the same time as the tunnels. For part of its 14 miles, up the Lyvia River valley to Wilmot Pass (2,200 ft) and down Dashwood Stream and Spey River valley, the highway follows the original tramping track over some of the most rugged country in New Zealand.

For two years men toiled in winter and summer to form the winding road to the summit, their progress slowed by snow, ice, and heavy rain. Small streams flooded by heavy rains trapped vehicles and rockfalls on new sections hampered the work.

Now concrete bridges span the streams, and although slips occur they are easily cleared. Machinery and supplies from overseas and coastal ships berthing at Deep Cove can be easily transported by road to the underground powerhouse at West Arm.

Previously closed, during the earlier part of the hydro works construction, Wilmot Pass road is now used by buses between West Arm and Doubtful Sound. The road has opened up wonderful mountain vista previously seen only by infrequent trampers.

Construction Brochure: Wilmot Pass, looking along Dashwood Valley to the pass and Doubtful Sound.
Wilmot Pass, looking along Dashwood Valley to the pass and Doubtful Sound.
Construction Brochure: Wilmot Pass road, construction work in progress.
Wilmot Pass road, construction work in progress.
Construction Brochure: Early construction of Wilmot Pass road in summer.
Early construction of Wilmot Pass road in summer.
Construction Brochure: Bridge abutment, Lyvia River, Doubtful Sound, on Wilmot Pass road.
Bridge abutment, Lyvia River, Doubtful Sound, on Wilmot Pass road.
Construction Brochure: Work starting on the bridge over the Lyvia River which flows into Deep Cove.
Work starting on the bridge over the Lyvia River which flows into Deep Cove.
Construction Brochure: Lyvia River bridge during construction.
Lyvia River bridge during construction.
Construction Brochure: Bridge crossing Spey River which runs into Lake Manapouri.
Bridge crossing Spey River which runs into Lake Manapouri.
Construction Brochure: Borland Canyon-Shallow Lake heading of transmission line access road.
Borland Canyon-Shallow Lake heading of transmission line access road. This road will connect with that being driven from South Arm up Grebe River Valley.
Construction Brochure: Typical cut on transmission line access road construction.
Typical cut on transmission line access road construction.

Transmission Line

From the switchyard above the powerhouse the transmission like will run southward crossing the mouth of the Spey River and then passing over the Turrett range by way of Wolf Flat, a plateau between 3,000ft and 3,500ft above sea level.

The route then runs down the valley of the Percy Stream to the Grebe River, up the Grebe Valley, across the Borland Saddle in the Hunter Mountains at 3,500 ft to the south branch of the Borland Burn, and thence to Monowai. It passes close to the Monawai power station, which was build in the early 1920s to supply Southland, and then runs generally south-east within a few miles of the historic mining townships of Ohai and Nightcaps, across the Southland Plains to Makarewa on the outskirts of Invercargill, and on to the smelter site at Bluff. Another line will connect the smelter to a substation of the national grid at Invercargill.

It is just over 100 miles from Awarua Bay (Bluff Harbour) to the generators at Manapouri. For 70 miles the route is in open rolling country; then abruptly it plunges into the rugged bush-clad mountains of Fiordland National Park. Here construction of the main access road and bridges was in itself a formidable and expensive task. The approaches to Wolf Flat are so steep that this sector, crossed by some 15,000 ft of line, will not be roaded. Flying foxes and probably helicopters will be used to reach transmission tower sites.

Construction Brochure: Bluff-Manapouri 220 KV transmission line map
Bluff-Manapouri 220 KV transmission line map
Construction Brochure: Air track dill on transmission line access route between Monowai and South Arm, Manapouri.
Air track dill on transmission line access route between Monowai and South Arm, Manapouri.

Control of Lake Manapouri

In the first stage of the Manapouri – Te Anau development there will be a low, rock-fill weir just below the confluence of the Waiau and Mararoa Rivers. By controlling the flow from Lake Manapouri it will tend to keep the minimum lake level a little higher than it might otherwise be.

For final development, however, it will be necessary to raise the level of Lake Manapouri substantially. This will be done by building in place of the weir a concrete dam and spillway to a height required to keep the lake at a level regarded as normally full. This is known as the controlled level.

The controlled level will be decided by engineering investigations, still incomplete, but it will not exceed 620ft. Probably it will be somewhere between 600ft and 610ft.

The most likely level, 610ft, is 27ft above the average natural level of 583ft and is 55 ft below the maximum controlled level permitted by the Manapouri – Te Anau Development Act.

The Act gave the aluminium company the right to raise Lake Manapouri 82ft above its average natural level which would have brought it to 666ft, the level of Lake Te Anau.

A controlled level of 610ft can be got by a simple and economical dam. Its estimated cost is less than £4,000,000. For this sum it will be possible to generate 350 million more units of electricity every year than if the dam were not built and the lake raised. This extra energy, at less than a farthing a unit, will be a good bargain.

Construction Brochure: Surprise Bay, Lake Manapouri
Surprise Bay, Lake Manapouri (left) and circle Cove (right) with Hope Arm in background.
Construction Brochure: Site of the Te Anau lake control
Site of the Te Anau lake control approximately 3 miles down the Waiau from Lake Te Anau. The weir will be at the cleared patch of brush on the bank, right centre.
Construction Brochure: The Manapouri weir
The Manapouri weir will be built approximately a mile below the area shown, below the meeting of the Mararoa Rivers.

Scenery Preservation

Construction Brochure: Lake Manapouri from Waiau river outlet.
Lake scenery worth preserving; Lake Manapouri from Waiau river outlet.

Fiordland is a national park vast in area and containing (in the words of the National Parks Act) “scenery of such distinctive quality or natural features so beautiful or unique that their preservation is in the national interest”. Many people would like to see Fiordland developed only enough to allow visitors to see its sights and enjoy the recreational activities it offers. However, some of the lakes and fiords that led to the 3 million acres being constituted as a national park make Fiordland a valuable source of hydro-electricity.

The national interest required the hydro-electric development, but the legislation authorising the scheme made particular reference to preservation of scenery. From the outset the project has been planned and executed to keep any harm to the natural features to a minimum. For instance, the major installation – the powerhouse at West Arm 0 is being built underground.

Planners, engineers, and construction staff have worked in harmony with those administering Fiordland National Park, even though the protection extended to the playful but destructive mountain parrot, the kea, has tried the patience of project workers at times. When the scheme is completed and construction scars are healed the scenery of the West Arm and Doubtful Sound regions will be unimpaired. One thing has been changed as a by-product of the power project: a region previously the preserve of a few hardy trampers and hunters is now wide open for all visitors to enjoy, with public transport running over the Wilmot Pass to Doubtful Sound.

Facts and Figures

Construction Brochure: Facts and Figures
Facts and Figures

Organisation

New Zealand Electricity Department manages all Government-owned generating stations and distributes electricity through its grid system to local supply authorities.

Ministry of Works is responsible to the New Zealand Electricity Department for all civil engineering work and has overall charge of the Manapouri project.

Bechtel Pacific Corporation, and American firm of engineers, retained as consultants. The corporation is in charge of engineering, procurement, and management of construction.

The work is being done in many separate contracts, including:

Tailrace Tunnel

Joint Venture – Utah Construction and Mining Co., San Francisco.
W.Williamson Construction Co. Ltd., New Zealand.
Burnett’s Motors Ltd., New Zealand.

West Arm Access Tunnel

Joint Venture – Morrison-Knudsen of New Zealand Ltd.
Downer and Co. Ltd., New Zealand.
Fletcher Construction Co., New Zealand.

Underground Powerhouse

Utah Construction and Mining Co., San Francisco.

Wilmot Pass Road

Joint Venture – Utah Construction and Mining Co., San Francisco.
W.Williamson Construction Co. Ltd., New Zealand.
Burnett’s Motors Ltd., New Zealand.

Transmission Lines Access Roading

Borland Canyon to Shallow Lake
Joint Venture – Herron Contracting Co. Ltd.
Darrel McGregor (Contracting) Ltd.

Grebe Valley to Percy Valley
Roadways (New Zealand) Ltd.

Wolfburn Section
D. H. Robinson Ltd.

South Arm Camp

Transmission Line Camp
R. Richardson Ltd.

Construction Brochure: Deep Cove
Deep Cove